Project Details
Location: Port Edward, BC
Time Frame: July 2018 – October 2018
Project Value: $900,000
Contract Type: Lump Sum
Services Rendered: Environmental & Demolition
Project Summary
Demolition of remaining structures at the former pulp mill site including two digester towers that were 280 feet tall and required significant engineering and pre-planning to topple and demolish. Morgan also managed waste caustic removal and chemical neutralization of residual waste as a cost effective alternative to packaging and offsite disposal.
Project Scope
Developed and executed safety protocols and strategies to safely demolish the "A-Mill" digesters, exhaust stacks, and structures that were 210 feet tall, utilizing engineering expertise and techniques
Removed and transported remaining waste and prepared the steel for further demolition, with the intention of selling it as scrap
Facilitated the sale of assets to international steel recyclers through brokerage services
Developed a new method using hydraulic jacking to overcome obstacles and successfully dislodge fixed dowels as part of the demolition process
Projects
Leaders in environmental and demolition services
Our proven track record of success in environment and demolition is what separates Morgan from the rest of the market. Take a look at some of our recent milestone projects.