Project Details

Location: Port Edward, BC

Time Frame: July 2018 – October 2018

Project Value: $900,000

Contract Type: Lump Sum

Services Rendered: Environmental & Demolition

Project Summary

Demolition of remaining structures at the former pulp mill site including two digester towers that were 280 feet tall and required significant engineering and pre-planning to topple and demolish. Morgan also managed waste caustic removal and chemical neutralization of residual waste as a cost effective alternative to packaging and offsite disposal.

Project Scope

  • Developed and executed safety protocols and strategies to safely demolish the "A-Mill" digesters, exhaust stacks, and structures that were 210 feet tall, utilizing engineering expertise and techniques

  • Removed and transported remaining waste and prepared the steel for further demolition, with the intention of selling it as scrap

  • Facilitated the sale of assets to international steel recyclers through brokerage services

  • Developed a new method using hydraulic jacking to overcome obstacles and successfully dislodge fixed dowels as part of the demolition process