Project Details
Location: Morinville, AB
Time Frame: August 2019 – September 2019
Project Value: $580,000
Contract Type: Lump Sum
Services Rendered: Environmental & Demolition
Project Summary
The demolition, removal, and disposal of an existing retail fueling facility include the building, fuel canopy, three underground storage tanks, three fueling dispensers, and all petroleum-related infrastructure. In addition to this work, the project includes excavation and removal of impacted soils.
Project Scope
Complete abatement removal and disposal of building hazardous asbestos-containing materials
General demolition of all identified components within the project boundary, including utility disconnects, kiosk, canopy, dispenser equipment, piping, conduit, vents, signage, lights, garbage enclosure, and all above and below-grade structural concrete, and asphalt or sidewalks/curbing
Removal and disposal of building structures, oil water separators, piping and foundations
Completed all required petroleum equipment removals, including the piping, distribution lines, dispensers, oil water separator and underground storage tanks upon purging and verifying a stable interior atmosphere
Excavation and removal of 8,000 tons of hydrocarbon-impacted soils
Removal and disposal of contaminated groundwater
Installation of liner along property lines as per soil management plan
Import fill, place and compact for all below-grade excavations and site restoration