Project Details

Location: Cold Lake, AB

Time Frame: November 2008 – 2023 (active)

Project Value: $300,000,000

Contract Type: Unit Rate

Services Rendered: Oil & Gas Construction

Project Summary

Morgan construction activities at Cold Lake started with the early civil works for the Nabiye Plant expansion project. The scope covers a breadth of work from timber salvage to rough grade of the entire plant site. This scope grew and included the 17km access road to the plant site and multiple km of access roads and 10 pad sites. Morgan continues to offer civil support for all expansion activities at Cold Lake including the recent GRP1 expansion project which is the largest production pad on site. Morgan has provided continuous support for existing facilities at Cold Lake. These scopes very from routine road maintenance to pipeline and well head excavations to construction of sprung structures. Our work within the existing plant sites includes below ground tank replacement, to lagoon waste hauls. Environmental scopes have included remediation and reclamation of drilling waste disposal sites, pad reclamations, tree planting and demolition of historical facilities.

Project Scope

  • Construct 11 production areas (150m x 200m) with access, 25-36 wells per pad, clearing and preparation of soil, building of rig pads, installation of conductor/cellar after drilling, and final grading

  • Construct 30 infill areas of varying sizes, extension of existing areas, with typically 4-9 wells per area

  • Clearing and preparation of soil, building of rig pads, installation of conductor/cellar after drilling, and final grading

  • Install a bridge with a 35-foot span over a creek crossing and develop a plan to control sediment and erosion

  • Dispose of drilling waste using mix-bury-cover and alternate methods, and reclaim associated areas where soil was borrowed

  • Construct a Class II landfill with an HDPE liner, working on day and night shifts due to a tight schedule, including during winter conditions

  • Conduct a winter oil sands exploration program, usually drilling 12-24 wells per year from 2008 to 2014

Nabiye Facility Plant Site Construction

  • Cleared and removed trees from 70.94 hectares of land while salvaging some of the timber

  • Removed 240,149 m3 of topsoil and 111,222 cubic meters of subsoil

  • Moved 590,000 m3 of soil to shape and level the land

  • Dug 35,000 m3 of temporary ditches for water drainage

  • Installed culverts to facilitate water flow

  • Installed riprap to protect against soil erosion

  • Added 8,100 m3 of gravel to create service roads, access roads, laydown and temporary parking areas

Nabiye Offsites

  • Removed 322,500 m3 of topsoil and 31,000 m3 of subsoil

  • Cut and fill 1,120,000 m3

  • Installed geotextiles to reinforce soil

  • Constructed a 17.5 km road with gravel base and asphalt concrete pavement to access the Nabiye site

  • Built a 100-foot bridge over a creek and developed a plan to prevent soil erosion during construction

  • Installed 1,200 mm CSP culverts and rock drains to cross two wetlands and prevent erosion

  • Built 25 well pads measuring 170m x 120m, including installing conductors/cellars, constructing rig pads, and final grading

  • Placed gravel on roads and well pads

  • Installed culverts and constructed ditches

  • Disposed of 82,650 m3 of drilling waste using new environmentally-friendly methods

  • Reclaimed and planted trees on about 50 hectares of land

  • Re-graded the Nabiye plant site after construction was completed

Projects

Our historic oil and gas profile

Our historic track record of success in the oil and gas sector is what separates Morgan from the rest of the market. Take a look at some of our recent milestone projects.

Oil & Gas Construction
Mine Development

TA9 Engineered Pond Bottom Cleanup

As our client progresses their mining operation, they intend to utilize a portion of the pit to store tailings which requires the installation of an engineered, competent base. A key component of this work is removing slop and unsuitable material from the existing ground that is left over from the previous mining operation.

Read More

Oil & Gas Construction
Mine Development

Mustang Haul Road

To facilitate the mining of valuable oilsand that lay below their existing main ore haul road, our client contracted Morgan to construct a 4.4 kilometer, 45m wide haul road that would serve as the new main artery for their fleet of 400T Haul Trucks for the next 10 years. A delayed start on the project compressed the already strict schedule, however Morgan successfully managed changes that arose from an incomplete design, material shortages, and unforeseen infrastructure conflicts to provide a completed project ahead of the required completion date. While working on this scope we handled over 1.5M cubic meters of sand and aggregates, and installed nearly 1500 lineal meters of large diameter carbon steel pipe culverts to strict quality standards.

Read More

Oil & Gas Construction

Cold Lake Nabiye and Projects

Morgan construction activities at Cold Lake started with the early civil works for the Nabiye Plant expansion project. The scope covers a breadth of work from timber salvage to rough grade of the entire plant site. This scope grew and included the 17km access road to the plant site and multiple km of access roads and 10 pad sites. Morgan continues to offer civil support for all expansion activities at Cold Lake including the recent GRP1 expansion project which is the largest production pad on site. Morgan has provided continuous support for existing facilities at Cold Lake. These scopes very from routine road maintenance to pipeline and well head excavations to construction of sprung structures. Our work within the existing plant sites includes below ground tank replacement, to lagoon waste hauls. Environmental scopes have included remediation and reclamation of drilling waste disposal sites, pad reclamations, tree planting and demolition of historical facilities.

Read More

Oil & Gas Construction
Mine Development

North Mine Advance – Reclamation Material Salvage

As part of Mildred Lake operations reclamation scope Morgan has been trusted to remove and salvage all surface soils and subsoils in advance of mining operations for the 2021 and 2022 reclamation seasons. Reclamation salvage is critical to our client’s operations as the surface soils must be stockpiled and stored to be reused at the end of the mine life. Morgan has successfully and safely removed and salvaged over 7.5 million m3 of soil during these two seasons resulting in a long-standing partnership.

Read More

Mine Development

Mildred Lake Extension - West Access Road

To facilitate the development of a new oilsands mine our client trusted Morgan with the construction of 10 km of access road. Included in this project was the construction of five major water crossings, two of which were large-diameter steel culverts and three concrete bridge structures on steel-driven piles. In addition to the 10 km of high-grade road, Morgan was also tasked with the construction of a permanent laydown area that will serve as the construction management team’s office location and material storage throughout the development of the new mine.

Read More

Oil & Gas Construction

Hardisty DRU Project

Civil site earthworks included supplying all equipment, labour, materials, and subcontractors to complete the earthworks site development and secondary containment of the midstream tank farm. Common excavation to fill, grading, construction of site access roads, approaches, culvert and ditching for site drainage, pond construction, berm construction, and four various-sized tank base foundations.

Read More