Civil Site Earthworks Construction
Conklin , AB
February 2012 to September 2012
Reimburseable, time and material
Oil & Gas
Project Summary:
Site Earthworks of CPF, 4 km highgrade road,tank bases , ponds, containment walls and culverts.
- 500 000m3 cut to fill rough grading
- 75 pieces of equipment
- Supply and placement of roadway and CPF gravels including sub base and base gravels
- Tank base preparation and containment walls
- Supply and installation of drainage csp culverts and ditch construction
- Excavation, gravel placement and drainage for tank foundations including geotextile
- Excavation and embankment construction for storm ponds including the supply and installation of HDPE liners
- Excavation, bed preparation and supply and installation of precast tank containment walls
- Supply and installation of HDPE tank containment liner complete with gravel cover
- Completion of work including GPS survey layout and machine grade control
- All riprap placement
- Detailed excavation and finish grading
Challenges and Achievements:
- Successful RFP process including Construction execution, HSE Management & Quality Management Plans
- 24 hour shift operations with 50 pieces of equipment utilized
- Maintained project schedule
- Maintained project budget
- HSE safety accomplishment – Lost Time Incident free project